Filters
Question type

Study Flashcards

If optimal sequencing through three work centers is desired, Johnson's rule II is used rather than Johnson's rule.

A) True
B) False

Correct Answer

verifed

verified

A manager must assign four engineers to projects, one to a project. The leader of project C has indicated that he does not want engineer 2 or 3 on his project. Given the following cost figures for each project-engineer combination, and keeping in mind that two combinations are undesirable, determine assignments such that total cost will be minimized. ABCD Engineer 1$1812201921718103252814428182425\begin{array}{rrrrr} & \mathrm{A} & \mathrm{B} & \mathrm{C} & \mathrm{D} \\\hline \text { Engineer }1 & \$ 18 & 12 & 20 & 19 \\2 & 17 & 18 & * & 10 \\3 & 25 & 28 & * & 14 \\4 & 28 & 18 & 24 & 25\end{array}  *undesirable \text { *undesirable }

Correct Answer

verifed

verified

blured image_TB2513_00...

View Answer

Scheduling in intermediate-volume systems has three basic issues: run size, timing, and sequence.

A) True
B) False

Correct Answer

verifed

verified

Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the critical ratio rule is used?  Job  Process Time  At This  Operation (hrs)  Process Time  At Remaining  Operations (hrs)  Final Due  Date (hrs) P648Q101540R51030 S81245 T6824\begin{array} { l c c c } \text { Job } & \begin{array} { c } \text { Process Time } \\\text { At This } \\\text { Operation (hrs) }\end{array} & \begin{array} { c } \text { Process Time } \\\text { At Remaining } \\\text { Operations (hrs) }\end{array} & \begin{array} { c } \text { Final Due } \\\text { Date (hrs) }\end{array} \\\hline \mathrm{P} & 6 & 4 & 8 \\\mathrm{Q} & 10 & 15 & 40 \\\mathrm{R} & 5 & 10 & 30 \\\mathrm{~S} & 8 & 12 & 45 \\\mathrm{~T} & 6 & 8 & 24\end{array}

Correct Answer

verifed

verified

The sequence will be P - T - Q - R - S. ...

View Answer

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:  Job  Processing  Time (hrs)   Due  (hrs from now)  V35 W11X49Y23Z57\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \mathrm { V } & 3 & 5 \\\mathrm {~W} & 1 & 1 \\\mathrm { X } & 4 & 9 \\\mathrm { Y } & 2 & 3 \\\mathrm { Z } & 5 & 7\end{array} If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in her shop today?


A) 2 jobs
B) 2.33 jobs
C) 2.4 jobs
D) 2.67 jobs
E) 3 jobs

F) B) and C)
G) All of the above

Correct Answer

verifed

verified

A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.

A) True
B) False

Correct Answer

verifed

verified

The EDD priority rule usually does well with regard to:


A) cost.
B) lateness.
C) overtime.
D) waste.
E) makespan.

F) C) and E)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is present in the manufacturing scheduling hierarchy but is absent in the service scheduling hierarchy?


A) aggregate planning
B) materials planning
C) master scheduling
D) detailed, short-term scheduling
E) detailed, short-term planning

F) None of the above
G) All of the above

Correct Answer

verifed

verified

Determine the processing sequence for the six jobs shown in the following table using Johnson's rule. Calculate total throughput time. Can the makespan be reduced by splitting the latest job? If so, by how much?  Processing Time (hrs)  Job  ST1  ST2  a 46 b 98 c 105 d 69 e 97 f 1210\begin{array}{ccc} & \text { Processing Time (hrs) } \\\text { Job } & \text { ST1 } & \text { ST2 } \\\hline \text { a } & 4 & 6 \\\text { b } & 9 & 8 \\\text { c } & 10 & 5 \\\text { d } & 6 & 9 \\\text { e } & 9 & 7 \\\text { f } & 12 & 10\end{array}

Correct Answer

verifed

verified

Schedule without splitting: makespan is ...

View Answer

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the average completion time for the earliest due date priority rule schedule? Average job tardiness? Average number of jobs at the center?

Correct Answer

verifed

verified

10.2 days;...

View Answer

To facilitate utilization of bottleneck operations, in theory of constraints scheduling ________ can be split into __________ to reduce waiting times.


A) bottleneck lots; nonbottleneck lots
B) transfer batches; process lots
C) sized lots; constrained lots
D) process batches; transfer batches
E) buffer lots; transfer lots

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

A work center can be a: (I) machine. (II) group of machines. (III) department. (IV) facility.


A) I, II, and III only
B) II and IV only
C) II and III only
D) I and III only
E) I, II, III, and IV

F) C) and D)
G) A) and B)

Correct Answer

verifed

verified

Eva, the owner of Eva's Second Time Around Wedding Dresses, currently has five dresses to be altered, shown in the order in which they arrived:  Job  Processing  Time (hrs)   Due  (hrs from now)  V35 W11X49Y23Z57\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (hrs) }\end{array} & \begin{array} { c } \text { Due } \\\text { (hrs from now) }\end{array} \\\hline \mathrm { V } & 3 & 5 \\\mathrm {~W} & 1 & 1 \\\mathrm { X } & 4 & 9 \\\mathrm { Y } & 2 & 3 \\\mathrm { Z } & 5 & 7\end{array} If Eva uses the shortest processing time first priority rule to schedule these jobs, what will be the average job tardiness?


A) 2 hours
B) 2.2 hours
C) 2.33 hours
D) 2.4 hours
E) 3 hours

F) B) and D)
G) B) and C)

Correct Answer

verifed

verified

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body paint work on each are as follows:  Car  Body Work  (hrs)   Paint  (hrs)   A 102 B 54 C 75 D 36 E 17\begin{array} { l c c } \text { Car } & \begin{array} { c } \text { Body Work } \\\text { (hrs) }\end{array} & \begin{array} { c } \text { Paint } \\\text { (hrs) }\end{array} \\\hline \text { A } & 10 & 2 \\\text { B } & 5 & 4 \\\text { C } & 7 & 5 \\\text { D } & 3 & 6 \\\text { E } & 1 & 7\end{array} Where in the optimum sequence should car A be scheduled?


A) first
B) second
C) third
D) fourth
E) fifth

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

Refer to the following data for jobs waiting to be processed at a single work center (jobs are shown in order of arrival):  Job  Processing Time ( days ) Due Date  (days from now) A22 B56C610D34E48\begin{array} { l c c } \text { Job } & \begin{array} { c } \text { Processing Time } \\( \text { days } )\end{array} & \begin{array} { c } \text { Due Date } \\\text { (days from now) }\end{array} \\\hline \mathrm { A } & 2 & 2 \\\mathrm {~B} & 5 & 6 \\\mathrm { C } & 6 & 10 \\\mathrm { D } & 3 & 4 \\\mathrm { E } & 4 & 8\end{array} What is the average completion time for the shortest processing time priority rule? Average job tardiness? Average number of jobs at the center?

Correct Answer

verifed

verified

10 days; 4...

View Answer

The assignment method is limited to a maximum of two jobs per resource.

A) True
B) False

Correct Answer

verifed

verified

There are three jobs to be done and three resources with which to do them. Each resource will cost a specific amount to do each job, as shown in the following table:  Machine  Job  A  B  C 1$69424433874\begin{array} { l c c c } & & { \text { Machine } } \\\text { Job } & \text { A } & \text { B } & \text { C } \\\hline 1 & \$ 6 & 9 & 4 \\2 & 4 & 4 & 3 \\3 & 8 & 7 & 4\end{array} What is the total cost for the optimum assignment of jobs to machines?

Correct Answer

verifed

verified

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:  Job  Processing  Due  Time (hrs)   (hrs from now)  W44X35Y22Z11\begin{array} { l c c } \text { Job } & \text { Processing } & \text { Due } \\&\text { Time (hrs) } & \text { (hrs from now) } \\\hline \mathrm { W } & 4 & 4 \\\mathrm { X } & 3 & 5 \\\mathrm { Y } & 2 & 2 \\\mathrm { Z } & 1 & 1\end{array} If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average job tardiness?


A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours

F) C) and D)
G) C) and E)

Correct Answer

verifed

verified

Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:  Process Time (Hours)  Job  Center A  Center B W45X66Y12Z52\begin{array} { c } \quad\quad\quad{ \text { Process Time (Hours) } } \\\begin{array} { l c c } \text { Job } & \text { Center A } & \text { Center B } \\\hline \mathrm { W } & 4 & 5 \\\mathrm { X } & 6 & 6 \\\mathrm { Y } & 1 & 2 \\\mathrm { Z } & 5 & 2\end{array}\end{array} If these jobs were scheduled in the sequence shown, when would idle time occur at machine B?

Correct Answer

verifed

verified

4 hours at...

View Answer

Use Johnson's rule to determine the optimum processing sequence for the jobs listed in the following table. Chart total throughput time.  Processing Time (mins)  Job  ST1  ST2  A 2012 B 1032 C 89 D 147 E 56 F 186\begin{array} { c c c } &{ \text { Processing Time (mins) } } \\\text { Job } & \text { ST1 } & \text { ST2 } \\\hline \text { A } & 20 & 12 \\\text { B } & 10 & 32 \\\text { C } & 8 & 9 \\\text { D } & 14 & 7 \\\text { E } & 5 & 6 \\\text { F } & 18 & 6\end{array}

Correct Answer

verifed

verified

\[\begin{array} { c c c c c }
\quad \qu...

View Answer

Showing 41 - 60 of 134

Related Exams

Show Answer